id: "01-queue-safe-normal-shard"
|
|
title: "Give the normal E2E shard a queue-safe budget"
|
|
status: completed
|
|
depends_on: []
|
|
plan: plan.md
|
|
spec: ../../specs/platform/requirements/e2e-duration-aware-sharding.md
|
|
parallelism: sequential
|
|
---
|
|
|
|
# Task 01: Give the normal E2E shard a queue-safe budget
|
|
|
|
## Acceptance
|
|
|
|
- The normal `e2e` matrix job uses a 35-minute job timeout.
|
|
- The container, desktop, report, and individual Playwright test timeouts stay
|
|
unchanged.
|
|
- The workflow contract test fails if the normal queue budget regresses to the
|
|
old 25-minute cap.
|
|
- The aggregate gate continues to reject cancelled jobs.
|
|
|
|
## Files
|
|
|
|
- `.github/workflows/e2e-tests.yml`
|
|
- `.github/scripts/e2e-tests-workflow-contract_test.py`
|
|
- `docs/specs/platform/requirements/e2e-duration-aware-sharding.md`
|
|
- `docs/plans/merge-queue-e2e-shard-timeout/plan.md`
|
|
|
|
## TDD sequence
|
|
|
|
1. Add the contract assertion and run it to prove the old 25-minute workflow
|
|
fails the new queue-budget requirement.
|
|
2. Change only the normal matrix timeout to 35 minutes.
|
|
3. Re-run the contract test and `git diff --check`.
|
|
|
|
## Operational verification
|
|
|
|
The merge-group run for the pushed PR must complete the normal shard matrix,
|
|
report merge, and `E2E Tests Passed` gate without a timeout removal event.
|
|
|
|
## Implementation result
|
|
|
|
- Changed only the normal `e2e` matrix job from 25 to 35 minutes.
|
|
- Added the queue-budget contract assertion.
|
|
- The RED contract run failed on the old timeout; the GREEN run passed all 5
|
|
contract tests.
|
|
- `git diff --check` passed.
|