id, title, status, wave, depends_on, plan, spec
id title status wave depends_on plan spec
05-capture-tool-definitions Capture tool definitions and estimates done 1
plan.md ../../specs/platform/requirements/mcp-session-observability.md

Task 05: Capture Tool Definitions and Estimates

Acceptance

  • The current Kandev catalog stores bounded input schemas from the actual tools/list response.
  • Each normal tool has a deterministic o200k_base token estimate for its complete compact MCP tool JSON.
  • The server reports o200k_base:mcp-tool-json-v1 when estimates are present.
  • A schema over 64 KiB is omitted and marked. All stored schemas stay within a 512 KiB combined limit.
  • Historical attempts contain no schemas or token estimates.
  • The tokenizer works offline. It does not use a character-count fallback.

Verification

cd apps/backend && go test ./internal/agentctl/types/streams ./internal/mcp/server ./internal/mcp/tooltokens ./internal/agent/runtime/lifecycle ./internal/orchestrator && go test ./internal/mcp/tooltokens -run TestKnownO200kVectors -count=1 && make build

Write failing tests for the wire contract, limits, history removal, and known tokenizer vectors before the implementation. Record the release-binary size before and after the dependency change.

Files likely touched

  • apps/backend/go.mod
  • apps/backend/go.sum
  • apps/backend/internal/agentctl/types/streams/mcp_attachment.go
  • apps/backend/internal/agentctl/types/streams/mcp_attachment_test.go
  • apps/backend/internal/mcp/server/server.go
  • apps/backend/internal/mcp/server/server_test.go
  • apps/backend/internal/mcp/tooltokens/estimator.go
  • apps/backend/internal/mcp/tooltokens/estimator_test.go
  • apps/backend/internal/agent/runtime/lifecycle/mcp_attachment_snapshot_test.go
  • apps/backend/internal/orchestrator/event_handlers_streaming_test.go

Dependencies

None. This task extends the completed Task 01 contract.

Parallelism

Sequential. Task 06 consumes the new optional fields.

Inputs

  • Spec sections Kandev tool catalog and Failure modes.
  • ADR 2026-08-18-session-mcp-tool-definition-details.
  • Existing mcp.Tool.MarshalJSON, AddAfterListTools, and catalog bounds.

Output contract

Report the wire fields, limit behavior, estimate method, dependency version, binary-size change, tests, blockers, and risks. Update this task and the plan status in the same session.

Results

Implemented the current-attempt tool-definition projection. Each tool can now carry a complete valid input_schema, an input_schema_truncated marker, and an estimated_tokens value. The Kandev server reports o200k_base:mcp-tool-json-v1 when estimates are available. Superseded attempts remove the schemas, estimates, estimator name, and catalog entries while they retain the tool count.

The projection keeps the existing 128-tool and 1,024-byte description limits. It omits a complete schema when it exceeds 64 KiB or when storing it would exceed the 512 KiB combined limit. It never stores partial or invalid JSON. Token estimates use the complete compact JSON produced by mcp.Tool.MarshalJSON before the bounded projection removes any fields.

Added github.com/tiktoken-go/tokenizer v0.8.1. It embeds the o200k_base vocabulary and works without a network connection. The first focused RED run failed nine assertions across wire retention, schema limits, MCP observation, and known tokenizer vectors. The GREEN run passed 322 tests in the three focused packages.

Release-size evidence from make build:

  • bin/kandev: 61,703,688 bytes before and 74,025,960 bytes after. The raw increase is 12,322,272 bytes.
  • bin/agentctl: 31,918,536 bytes before and 43,769,224 bytes after. The raw increase is 11,850,688 bytes.
  • Comparable gzip output increased by 3,035,259 bytes for kandev and 2,925,001 bytes for agentctl.

The compressed increase is close to the required vocabulary size. A smaller alternative would download data at runtime, use an inexact heuristic, or add a shared external-data contract to every launcher. The implementation keeps the reviewed exact offline behavior.

Verification passed from apps/backend:

go test ./internal/agentctl/types/streams ./internal/mcp/server ./internal/mcp/tooltokens ./internal/agent/runtime/lifecycle ./internal/orchestrator
go test ./internal/mcp/tooltokens -run TestKnownO200kVectors -count=1
make build

The build completed with the existing warnings that cross-built Darwin agentctl binaries were not code-signed locally.