id, title, status, wave, depends_on, plan, spec
id title status wave depends_on plan spec
04-e2e-coverage Desktop and mobile E2E coverage done 3
02-backend-issue-workflow
03-frontend-dialog-and-mobile
plan.md ../../specs/improve-kandev/spec.md

Task 04: Desktop and mobile E2E coverage

Acceptance

  • Desktop Playwright proves intro dismissal persistence, direct reopen, report-only task creation, and EMU implementation-versus-issue gating.
  • Mobile Playwright opens the feature through Open menu → Improve Kandev, proves 44px touch targets, reaches Open issue, and detects no document horizontal overflow.
  • Both specs pass against the production Vite build served by the Go backend.

Verification

cd apps/web && pnpm e2e:run tests/improve-kandev.spec.ts
cd apps/web && pnpm e2e:run --no-build tests/mobile-improve-kandev.spec.ts -- --project=mobile-chrome

Files likely touched

  • apps/web/e2e/tests/improve-kandev.spec.ts
  • apps/web/e2e/tests/mobile-improve-kandev.spec.ts

Dependencies

Tasks 02 and 03.

Parallelism

Sequential. These specs share the Improve Kandev route mocks and production build.

Inputs

  • All spec scenarios for dismissal, issue reporting, fork restrictions, auth, and mobile access.
  • Plan: E2E Tests and Continuation Snapshot.
  • Existing fixture APIs in apps/web/e2e/helpers/api-client.ts.

Completed implementation notes

  • Desktop tests for persistence, issue task workflow, and revised EMU behavior are already drafted. The focused persistence and issue-submission tests passed individually.
  • The mobile spec is drafted. Its initial sidebar-based path failed because the desktop footer is hidden on phones; the test now uses the mobile menu.
  • The mobile utility entry was rebuilt and verified after the initial sidebar path was corrected to use the native mobile menu.

Recorded verification

  • cd apps/web && pnpm e2e:run tests/improve-kandev.spec.ts — passed (7 desktop tests).
  • cd apps/web && pnpm e2e:run --no-build tests/mobile-improve-kandev.spec.ts -- --project=mobile-chrome — passed (1 mobile test).
  • The first rebuilt mobile run caught a 43px preference target; the intro checkbox label was increased to min-h-12, then the rebuilt mobile run passed with the required touch target and no horizontal overflow.

Task 04 is complete. Continue with Task 05 for repository verification and commit.

Risks

  • Route mocks must return both workflow IDs, and the submitted issue workflow must exist in the E2E backend before asserting its start step.
  • Do not increase Playwright timeouts; inspect error context if the mobile drawer-to-dialog handoff races.

Output contract

The desktop and mobile Playwright suites prove the shared flow, touch-target requirements, report-only workflow, and mobile containment behavior.

Update this task and plan.md, report both exact commands and outcomes, include fresh failure-artifact paths if any, and state whether rendered mobile containment/touch behavior is proven.