Plans and Work Orders

Purpose

Plans and work orders are delivery records. They describe how a change moves the current system toward its requirements and system design.

They are not living product specifications.

Plan

docs/plans/<initiative>/plan.md is the work-package manifest. It contains the delivery overview, dependency order, risks, verification strategy, and links to each work order.

A plan references the applicable requirement documents and system designs. It does not copy their content.

Work order

Each task-<NN>-<slug>.md file is one work order. A work order contains:

  • A short outcome summary.
  • In-scope responsibilities.
  • Explicit exclusions.
  • Applicable REQ-* and AC-* identifiers.
  • Applicable system-design paths.
  • One to three implementation acceptance conditions.
  • Exact verification commands.
  • Likely files and dependencies.
  • Results after implementation.

Use a separate work order when work has an independent result or verification boundary. Do not split work only by backend and frontend layers when a vertical slice can remain functional.

Verification

Every work order owns the verification that proves its implementation result. Use unit, integration, or end-to-end tests at the appropriate boundary.

A user-facing requirement needs end-to-end evidence somewhere in the work package. A low-level work order does not need an artificial browser test.

Reference acceptance-criterion IDs from tests when that reference improves traceability.