Plans and Work Orders
Purpose
Plans and work orders are delivery records. They describe how a change moves the current system toward its requirements and system design.
They are not living product specifications.
Plan
docs/plans/<initiative>/plan.md is the work-package manifest. It contains the
delivery overview, dependency order, risks, verification strategy, and links to
each work order.
A plan references the applicable requirement documents and system designs. It does not copy their content.
Work order
Each task-<NN>-<slug>.md file is one work order. A work order contains:
- A short outcome summary.
- In-scope responsibilities.
- Explicit exclusions.
- Applicable
REQ-*andAC-*identifiers. - Applicable system-design paths.
- One to three implementation acceptance conditions.
- Exact verification commands.
- Likely files and dependencies.
- Results after implementation.
Use a separate work order when work has an independent result or verification boundary. Do not split work only by backend and frontend layers when a vertical slice can remain functional.
Verification
Every work order owns the verification that proves its implementation result. Use unit, integration, or end-to-end tests at the appropriate boundary.
A user-facing requirement needs end-to-end evidence somewhere in the work package. A low-level work order does not need an artificial browser test.
Reference acceptance-criterion IDs from tests when that reference improves traceability.