# Plans and Work Orders ## Purpose Plans and work orders are delivery records. They describe how a change moves the current system toward its requirements and system design. They are not living product specifications. ## Plan `docs/plans//plan.md` is the work-package manifest. It contains the delivery overview, dependency order, risks, verification strategy, and links to each work order. A plan references the applicable requirement documents and system designs. It does not copy their content. ## Work order Each `task--.md` file is one work order. A work order contains: - A short outcome summary. - In-scope responsibilities. - Explicit exclusions. - Applicable `REQ-*` and `AC-*` identifiers. - Applicable system-design paths. - One to three implementation acceptance conditions. - Exact verification commands. - Likely files and dependencies. - Results after implementation. Use a separate work order when work has an independent result or verification boundary. Do not split work only by backend and frontend layers when a vertical slice can remain functional. ## Verification Every work order owns the verification that proves its implementation result. Use unit, integration, or end-to-end tests at the appropriate boundary. A user-facing requirement needs end-to-end evidence somewhere in the work package. A low-level work order does not need an artificial browser test. Reference acceptance-criterion IDs from tests when that reference improves traceability.